Phase 5 HRA New Build Sites
3 Sites with Associated Extensive External Works
Total Project Value: £1.5 million
Project – Gaitskill Crescent
Dwellings – 2 Bungalows with a value of £446,978
Duration – 21 Weeks
Completed – 18th July 2024
Project – Fir View
Dwellings – 2 Bungalows with a value of £570,000
Duration – 30 Weeks
Completed – 6th November 2024
Project – Manor Close
Dwellings – 1 Bungalow with a value of £300,000
Duration – 16 Weeks
Completed – 14th October 2024
Each site had its own challenges from boundary and drainage issues to planning and highways. All were dealt with working closely with the design and team and Newark and Sherwood.
Working closely with our timber frame specialists Oakworth Homes, we provided highly insulated environmentally conscious homes
Project Highlights
Health and Safety – Safety first works as no accidents reported through construction.
One team approach – Without an open and honest partnership challenges would not have been overcome.
Environmentally conscious Homes – Utilising a fabric first approach with our timber frames combining with air source heat pumps.